Radiant Coil
Repair Procedure in Cracking Furnaces]
|
This procedure applies
to Cracking Furnaces ( 11-FH-201/205)
Contents.
1 Terminology
2 EQUIPMENT NAME (SERVICE)
3 TAG NUMBER OF EQUIPMENT
4 RESPONSIBILITIES
5 SAFETY, HEALTH & ENVIRONMENT
PRECAUTIONS
5.1
PROTECTIVE EQUIPMENT
6 MATERIAL NEEDED
7 TOOL LIST
8 MAINTENANCE PROCEDURE
9 CHECK LIS
10 DEVIATIONS FROM PROCEDURE
11 SUGGESTION FOR improvement
12 References & Attachments
1.0 TERMINOLOGY:
Key terminology used in this
document is either defined on its first occurrence or takes the common
definition as stated in the;
1.1 WPS: Welding Procedure specification.
1.2 ID Fan: Induced Draft Fan
1.3 DM Water: Demineralized
Water
2.0 Equipment Name:
Cracking Furnace Radiant Coils
3.0 Tag
Number of equipment:
Radiant
Coils for Furnace 11-FH-201/205
4.0 Responsibilities:
1.
Shift Supervisor( Operations)- For making system ready for maintenance.
2.
Maintenance Supervisor: For Job execution and Job planning before the start of
the job and history Updating.
3.Maintenance Technician: To follow work
instruction and time logging.
4.Maintenance Engineer: To ensure the
availability of the procedure for the job.
5.0 Safety and Environmental
Precausions:
5.1 The
radiant coils will become very brittle in nature in aged condition. Hence the
coils need to be supported at several places if coils are to be cut for
maintenance.
5.2 The
location of joint has to be decided keeping in view of the safety of the
persons working and welder convenience.
If possible the joint to be made at floor level.
5.3 When
persons are working in the fire box, ensure that radiant coils are not blown
with Nitrogen.
5.4 Ensure
that ID Fan is running and firebox is sufficiently ventilated.
5.5 Only 24
Volts hand lamps should be used in side the firebox.
5.6 All the
hydrocarbon lines are to that Furnace to be positively blinded.
5.7 Scaffolding/ Platforms to be arranged as per
standards.
5.8 Fire box
manholes on both sides to be opened for persons to enter into the firebox.
5.9 Before cutting the coils, ensure that they are
supported at as many locations as possible with the help of chain blocks, nylon
ropes.
5.1 Personal Protective equipment to be used:
- Hard hat
- Eye protection
- Safety belt for the welder
- Safety shoe
- Dust mask
- Disposable Coveralls
6.0 Materials Needed:
- Filler wires as per the “WPS”
- Scaffolding material.
7.0 Tools required:
1.Chain Blocks( 1
or 2 Tons capacity)
2. Nylon rope
3. TIG- welding
set with necessary filler wires( See attachments for Details)
4. Clamps for fit
up.
5. Thermo chalks
6. Boroscope to check inside the coil
7. Hydrojetting
machine if the coils need dechocking.
8.0 Maintenance Procedure :
8.1 The following permits to be obtained from Operations department for
radiant coils repair job:
1. Cold work Permit.
2. Hot Work permit.
3. Confined space entry permit
8.2
Cutting / Edge preparation and Rewelding:
1. The orientation markings to be made before
cutting the coils. Otherwise the fit up will be proper as they have bow.
2. Ensure
that nitrogen pressure is not there in the coils before cutting and minimum thickness
of the cut off wheel should be used to part the coil.
3. The coil
parts are to be taken out of the fire box for dechocking by hydrojetting.
4. Ensure
that the markings made on the coil with crayons do not contain sulfur.
5. See the
attached WPS for the details related to the edge preparation, filler wire
specification, and Procedure.
6. Ensure
that interpass temperature does not go
beyond 150 Deg C.
7. For
rewelding, the clamps can be used for proper fitup and Tack welding. Ensure the
sufficient inert gas flow inside the coil.
In this case ,the pure
Dry nitrogen from utility header can be
used. Ensure that ID Fan is running and maximum air is sucked through the fire
box in which welding is to be carried out. Keep monitoring the oxygen level at
the work place continuosly and masking tape is to be used to minimise the
nitrogen coming in to the fire box during welding. The persons involved in this
needs to be given tool box talk accordingly.During execution of the welding
when nitrogen is used for purging portable Oxygen alarm to be used. A radio
communication has to be established
between welder and the Operator who has to immediately close the nitrogen valve
in case of unacceptable nitrogen concentrations in the work place.
8.3 WPS :
For WPS( Welding procedure Specification) See attached WPS by the supplier of the
coils” Paralloy Limited”
8.5 Inspection:
1.Inspection will be as per “
WPS”
2.Pneumatic Test
to be done before taking coils into line.
3.All fit up
markings to be removed or to be cleaned with some solvent.
8.6 Normalizing the system:
1. All blinds to be normalised.
2. Leak checking to be done for all disturbed
flanges at operating pressure.
3. Work
permits to be closed and returned to Operation Department
4. All high
temperature flanges are to be hot bolted when furnace being brought up.
9.0 Check
lists : NA.
10.0 Deviations from Procedure
Deviations from the requirements of this procedure are not
permitted without a written waiver formally authorized and recorded in
accordance with the “Incident Reporting” procedure.
11.0Suggestions FOR IMPROVEMENT
Employee contribution to the effectiveness of the way
Borouge conducts its business is welcomed. Any employee of Borouge may suggest
changes / revisions to this procedure by completing a “Request for Improvement”
form as per the “Incident Reporting” procedure.
Request for Improvement” form as per the “Incident
Reporting” procedure.
12.0Reference and Attachments:
WPS by the supplier” Paralloy Limited”
2 comments:
These are very great tips for a homeowner who is looking for a better HVAC contractor. Air conditioners, furnace needs maintenance which is undertaken with good hands. Heating and Cooling Newmarket
Thanks for sharing content and such nice information for me. I hope you will share some more content about. Please keep sharing! Putas bogota
Post a Comment