8.1 QUESTIONS
1. What are the
principal voltages used in England and Wales for the bulk transportation of
power? Which are operated by the CEGB
and which by the Area Electricity Boards?
2. At what voltages
and frequency do large and small consumers in the UK receive their power?
3. At what voltage
do the large power station generators operate?
4.
What do
you understand by ‘unit construction’ of a generation system?
5.
A
transmission line is to be 90 miles long. What would be the optimum operating
voltage? What standard voltage would probably be chosen?
6.
How is
domestic voltage obtained at ‘street’ level (a) in the UK, (b) in the USA, (c)
on an offshore installation?
7.
How is the
national frequency level in the UK controlled?
8. How are voltage
levels in UK networks controlled?
9. What is the
statutory limit on voltage variation of power supplied to consumers? Whose responsibility is it?
10. What can an
industrial consumer do to regulate his voltage?
11. What do you
understand by the term ‘infinite busbar’?
12. How is the
infinite busbar concept used?
13. What effect would
increasing load have on an 11kV distribution line? How can it be regulated?
14. What effect would
increasing load have on a 400kV transmission line? Why the difference from Q13? What action can the Control Engineer take?
15. Where does a
typical onshore installation draw its power from? How is it supplied, and at what voltage?
16. Who owns the
installation’s main supply transformers?
17.
If there
is more than one supply source, what steps are taken to keep them separate?
18. What
type of switchgear is usually provided for the high-voltage incomers to the
onshore installation and for the high-voltage feeders?
19. What steps are taken to ensure the
maximum reliability of supplies to the LV distribution systems?
20. If all external power supplies to an
onshore installation are lost, what steps are taken to
ensure continuation of the minimum vital supplies?
21. Why are tariffs in two parts?
22. If an industrial consumer’s maximum
kVA demand is higher than it need be, what can he do to reduce it?
8.2 ANSWERS
(Figures in brackets after each answer refer to the relevant chapter
and paragraph in the text.)
1.
Transmission
voltages: 400kV
|
CEGB
|
275kV
|
|
Distribution
voltages: 132kV
(formerly transmission)
|
Area
|
33kV
|
Electricity
|
11kV
|
Boards
|
|
(3.2)
|
2. Large consumers 11kV (a few at 33kV)
at 50Hz.
Small consumers 415V (4-wire)
(giving 240V, single-phase) at 50Hz. (3.2)
3. Previously between 11kV and 22kV,
now more commonly 25kV. (3.2)
4. Unit
construction is where the generator terminals are solidly connected to the
primary terminals of the step-up line transformer, with no intervening
switchgear. The prime mover, generator
and transformer form a single electrical unit.
The first switching control is the circuit-breaker on the HV side of the
step-up transformer.
(3.2)
5. At
1.2kV per mile, the optimum operating voltage would be about 90 x 1.2 =
108kV. The nearest standard 132kV would
probably be chosen. (3.2)
6. (a)
Street distribution in the UK is at
415V 50Hz 3-phase 4-wire from street pillars.
Domestic supplies would be taken off line-to-neutral at 240V,
single-phase.
(b) In
the USA street distribution is at 440V 60Hz 3-phase 3-wire. Domestic supplies are transformed from this
to 1 17V single-phase.
(c) On
offshore installations LV distribution is at 440V 60Hz 3-phase 4-wire. Domestic supplies are taken off
line-to-neutral at 254V single-phase. (3.2)
7. National
frequency is closely monitored, and the gain or loss is indicated by gain or
loss of cycles compared with a standard.
If there is a continuing loss, more energy is being taken out of the
national network than is being put in.
The National Control Centre orders certain running stations to take on
more load, or orders standby stations to start up and take on load, until
balance is restored and the lost cycles recovered. (3.3)
8. Voltage
levels at various points of their networks are monitored by the CEGB Regional
Control Centres, and correcting action is taken. This may be by AVR adjustment, by transformer
on-load tap changing or by use of reactors
(3.3
& 4.3)
9. ±6%. Maintenance of these limits is the
responsibility of the Area Electricity Boards in England and Wales, and of the
NOSHEB or SSEB in Scotland. (3.3)
10. Very
little, unless he has on-load tap changing. If his supply is outside the ±6%
limit and he cannot get his Area Electricity Board to correct it, he can only
change his transformer taps which, being probably of the off-load type, would
entail shutting down while the tap is changed. (3.3)
11. It
represents a source of supply of such a large capacity that it has no limit.
Also its source impedance is regarded as zero, which means that there is no
frequency regulation and no voltage regulation as load changes. It thus
represents an infinitely large generator with perfect governing and perfect
voltage regulation. (4.2)
12. Where
the National Grid supplies a consumer installation of limited size, the massive
backing of the grid system can be regarded as an ‘infinite busbar’ relative to
the limited consumer network. (4.2)
13. An
11kV distribution line, having both resistance and inductance, will cause an
increasing voltage drop as load increases, especially if that load contains a
reactive part. Such voltage drops can be
compensated for by on-load tap changing within the distribution system. (4.3)
14. A
400kV line presents a large fixed capacitance to the power source, and the
capacitive current which consequently flows causes a voltage rise in the
line unless offset by a voltage drop due to other causes. Such a cause would be normal loading, where
the reactive component causes a voltage drop.
Thus for low loading there would be a net voltage rise, but as the
loading increased the amount of rise would become less until, at some point,
there was a balance and no voltage rise or fall at all. A further increase of loading would produce a
net voltage fall.
The Control Engineer can compensate for voltage rise (which occurs
during periods of low power such as at night or weekends) by on-load tap
changing, by AVR control of generators or by switching-in reactors to absorb
the leading megavars. (4.3)
15. From
two or more bulk supplies provided by the Supply Authority. They are supplied at extra-high voltage (at
least 132kV) and transformed down to 33kV or 11kV at the installation’s bulk
supply point. (5.1)
16. The
EHV grid transformers, and their HV switchgear, remain the property of the
Supply Authority. (5.1)
17. The
incoming supplies, which are usually derived from different sources, are
separated by a section breaker at the HV switchboard. This section breaker is normally kept open,
and each supply source feeds separate parts of the installation. Interlocks prevent both incomers and the
section breaker being closed together, so avoiding paralleling the two
sources. Similar interlocks on the LV
switchboards prevent paralleling through the transformers.
If one supply source fails, its incomer breaker is locked open and
the section breaker automatically closes, so restoring supply to the failed
half of the board.
(5.2.1)
18. Oil
circuit-breakers. (5.2.1)
19. Every
LV switchboard has two alternative incomers from separate transformers fed from
the two sides of the HV switchboard; these are fed from different external
supply sources. Thus the failure of an
external source, of a transformer or of a cable does not deprive an LV board of
power. The alternative is available and
takes over the whole board by automatic closing of the section breaker, as in
Answer 17 above. Each of the alternative
transformers and cable systems is designed to carry the full load on its own. (5.2.4)
20. In the
unlikely event of all external supplies being lost, an emergency diesel-driven
generator automatically starts and takes over a limited amount of the LV
load. This is done through ‘secure
power’ switchboards to which the most vital consumers are connected. (5.2.4)
21. Tariffs have a variable part to
recover cost of energy actually consumed - and hence of fuel burnt - and other
running costs. They also have a fixed
part, independent of energy consumed, to recover a contribution to the capital
cost of the whole power installation. This fixed part is usually related to a
consumer’s maximum demand, averaged over successive 30-minute periods, during
any one accounting period. (6.2)
No comments:
Post a Comment